Thursday was about getting the drains in and the oversite ready for the buildings inspector. He gave it the nod and the damp proofing membrane went in, followed by metal reinforcing bars and lastly concrete. We now have the beginnings of a floor! Paul and the kids have added some graffiti in the concrete which my deep conformism has been rather troubled by.
| Digging a hole for the electricity cable. |
| How we used to get electricity. |
| The old wires going to the neighbour's pole. |
| It's all gone! |
| Aggregate in first |
| And at the back |
| The last of the spoil has gone so the front garden looks quite big now. |
| Aggregate tamped down (that was a bit noisy). |
| DPM on and metal reinforcements ready. |
| The concrete has arrived. |
| The first barrowful of our new floor. |
| Concrete being laid. |
| Making a beautiful smooth surface. |
| The first part of the floor is in. Insulation, a concrete layer with the underfloor heating and a layer of screed to go on top of this. Mostly smooth apart from the graffiti (breathe deeply). |