Tuesday, 28 May 2013

Week 6

The downstairs walls are now built and the outside insulation on ready for rendering.  The upstairs front and back walls are also built and the scaffolding has gone up another 2 layers ready for the roof to be built in week 7.  Some torrential rain on Friday and builders holidays meant not much went on that day but otherwise another busy week.

The upstairs walls are started and the bedroom and bathroom floors are in

The flat roof has been sloped, covered and painted with waterproof paint.  The felt will go on later.

The back corner of the kitchen looking at the back wall of the bedroom.

The outside insulation and covering is on.

Closer to the insulation and mesh ready to take the render.

More scaffolding is up and the upstairs is taking shape.

Looking down from the scaffolding to the upstairs floor.

This scaffolding will be used to build the roof.
The bathroom wall at the front of the house with the hole for the window.  The upstairs floor is chipboard but covered in a waterproof layer which is just as well as Friday was a deluge.

Nice view of the garden from the scaffolding.


Friday, 17 May 2013

Week 5

It has been an exciting week as we have left the ground!  Our walls are to be timber framed and the timber arrived on Monday.   Since then the guys have worked hard and we have our ground floor walls, the joists for the flat roof are in and the scaffolding is in for the upstairs.  A large steel joist is in place to support the upstairs wall and a concrete base has been put in for the boiler house.

The render is off in the corner showing just how little insulation there is upstairs

The start of the walls (and the rain)

The walls taking shape at the back

The rain has gone and the walls are filling in

The steel joist which will support the upstairs wall

The scaffolding is going up

The side wall is wrapped in wood

The joists for the flat roofed section are in

The back of the house showing the spaces for the office window and the french windows from the kitchen.

Friday, 10 May 2013

Week 4

It's been a bit of a stressful week this week but things have moved on.  Monday was bank holiday so peace and quiet for the day.  Tuesday and Wednesday were scheduled to have the overhead electricity supply moved underground.  This proved to be a huge operation.  The supply comes from a pole in the neighbour's garden so they had to have some of their patio lifted.  It also affected the neighbour attached to us as her electricity supply goes into our house, through our roof and to her meter.  The electricity co would not let us do that again so she had to have her drive and garden dug up and a cable put up the front of her house.  All of which she found extremely stressful.  So, the digging happened on Tuesday and then the next crew came on Wednesday to do the connections.  I had my electrician on hand.  All went reasonably well until it came to the connection of our neighbour's supply.  It seems her electricity is in a parlous state as she had no earth, her pipework was not bonded and her circuit breaker was not working.  The connection guys refused to connect to an unearthed circuit.  Panic!  In the end our electrician did a temporary bodge to provide an earth and the connection was completed.  Our neighbour was distraught and terrified of bills of hundreds of pounds to sort her electrical system.  I spent most of Thursday morning on the phone and think I have found a grant which can help pensioners keep their homes in a decent state of repair.  Hopefully, she will end up with a much safer system in the end but it has been painful getting there.

Thursday was about getting the drains in and the oversite ready for the buildings inspector.  He gave it the nod and the damp proofing membrane went in, followed by metal reinforcing bars and lastly concrete.  We now have the beginnings of a floor!  Paul and the kids have added some graffiti in the concrete which my deep conformism has been rather troubled by.

Digging a hole for the electricity cable.
How we used to get electricity.


The old wires going to the neighbour's pole.
It's all gone!

Aggregate in first
And at the back


The last of the spoil has gone so the front garden looks quite big now.


Aggregate tamped down (that was a bit noisy).

DPM on and metal reinforcements ready.

The concrete has arrived.

The first barrowful of our new floor.

Concrete being laid.

Making a beautiful smooth surface.

The first part of the floor is in.  Insulation, a concrete layer with the underfloor heating and a layer of screed to go on top of this. Mostly smooth apart from the graffiti (breathe deeply).



Monday, 6 May 2013

Week 3

The retaining wall by the stream was finished early so there were a couple of quiet days during the week but it all got noisy again near the end of the week when the walls which will support the timber frame were built.  I spent time trying to decide what flooring to have in the kitchen diner.  I visited a lovely chap in his factory making hand made Norfolk pamments but have also seen some rather beautiful large tumbled white limestone slabs.  I've investigated reclaimed floors but they are eye-wateringly expensive.  It's such a dilemma.  Anyway, here are this week's photos:

Gravel being delivered to fill behind the retaining wall to the stream.  This lorry also took a lot of spoil away (lorry number 8!)

Moving the gravel.

Filling the back of the wall

Digging a channel to the drain

Getting ready to build the wall

Another view

This is the finished foundation wall up to floor height.  Next week we'll get a concrete floor.

Another view