Thursday, 3 October 2013

Week 25

Its been a long time since I added anything as it all went very quiet for some weeks.  However, things are now moving on.  We have got the underfloor heating working and have laid the slabs in the big room.  The boiler is also pumping out lots of lovely hot water so we can use the new bathroom.  This has meant that Alan and co can move into the old kitchen and bathroom.  Paul and I spent a weekend carefully removing the old kitchen and setting it up as a temporary kitchen where the new one will eventually go.  The the guys came and ripped everything out.  They have blocked up old doors, opened new ones, removed and replaced ceilings (now with insulation in them!). 

The downstairs shower room is coming along and is in the process of being tiled.  We are using white metro tiles over all the walls which is very clean and bright but possibly a bit urinal like!

Oh, and we now have doors.  Pine was almost impossible to source at a reasonable price so we have oak and very well they look too.  We also have a back door but apparently a back doorstep is an optional extra so we have a big drop outside the door!

The old ceiling in the kitchen including some original lime plaster

Gary removing the bathroom

The new wall between the dining room and old kitchen

The kitchen part dismantled

More kitchen being taken apart


The old bathroom door has been filled in and a new opening made

The opening for the back door

The opening for the new back door (temporarily covered by a board) and the old entrance to the back porch (now blocked and plastered)


The new room with temporary kitchen

From the other end

Door to the study

The old dining room is slowly becoming the snug

Temporary kitchen

New back door (with 2ft drop!)

Downstairs shower room in process of being tiled

Door between old kitchen and old dining room