Sunday, 16 June 2013

Week 9

A busy week and it really feels like we're moving forwards.  The roofing has all been finished and the entire extension rendered.  We now have the beginnings of a wall between the bathroom and the bedroom, the loft has been boarded and the hatch ladder installed.  We've also had some of the wiring put in for the lights and sockets. I need to paint the render next week and actually really like the colour of the naked render so will probably be trying to get something similar in paint.  Also looking forward to windows next week.

Th wall between the bathroom and the bedroom (from the bedroom side)

The hatch and ladder to the loft

The loft

The back with the render

The front and side with render

The front of the house