Saturday, 20 April 2013

Week 1

The end of the first week and there is certainly some change.  The backporch and workshop have gone, tonnes of concrete have been noisily smashed and taken away, the foundations dug and filled with concrete.  The best news is that the buildings inspector visited and was happy with the depth of the foundations and we don't need any fancy (and expensive) extra support.

We are now spending a sunny Saturday burning lots of old wood (cheaper than having it taken away).

Digging out the workshop floor (we found the base of a smaller shed beneath this)

The lorry to take the concrete away.  It needed two trips to take it all.

The lorry filling up

The new space marked in blue

This is where the walls will be

The start of the foundations

More foundations.  Note that it is deeper (1.8m) at the corner nearer the stream

More foundations being dug and a spoil heap getting bigger (and unfortunately covering the carefully saved topsoil plus a few nice plants)



It took a while to get the concrete lorry reversed down the drive......

But it got here in the end.  We needed two lorries to fill the foundations.

We were quite pleased to find the original house foundations went down further than we had expected

The second load of concrete was trucked in from the mixer which stayed at the end of the drive.

The foundations with concrete.

This fire has been burning for 2 days and we still have a garden full of timber!

The concrete is drying and the portaloo has arrived.

The corner nearest the stream.

So much for the front garden.  We'll have a bit of tidying and remodelling to do there.  Note the oil tank which was moved.