Friday, 26 April 2013

Week 2

I've been away in Dartford for most of the week.  While I was away the site was levelled and the retaining wall for the stream has been started.  No work on Tuesday as the steel had not arrived but from Wednesday onwards the team have been busy building the wall.  The blockwork is now ready for the concrete to arrive on Monday to fill the centre of the wall.  It will then be capped at ground level and backfilled.

  
The steel arriving for the retaining wall

Digging the footings

Digging the footings
Preparing the footings

Footings dug and steel reinforcements in

Concrete footings in

The starts of the blocks

A couple more layers of blocks and the structure will be ready for the concrete centre

View from the front garden

View from the front garden

Almost finished the blockwork and the sandbags have been added to protect the ends


1 comment:

  1. Little worried about the stability of the Porta-Loo!

    ReplyDelete